The basins in the left section of the drinking water treatment plant were rehabilitated. The work included removing old resides, replacing the bases of sand filters and filtration ele-ments, as well as the raw water circuits, treated water circuits, electrical control systems, and air circuits, Architectural restoration was also carried out, along with the integration of GRP panel technology. These works were implemented under the supervision of a non-governmental organization (NGO)
حالة المشروع:
المشاريع المنجزة
المدة:
120 يوم
المحافظة:
Aleppo
سنة المشروع:
2025
الطرف المتعاقد:
ZOA